Projects

Our Accomplished Projects


220KV Substations


220KV Substations   Client: Ministry of electricity & Water
Consulting Engineer: MEW
Main Contractor: CEBARCO BAHRAIN SP
Location: Three locations throughout Bahrain
Contract Period: 10 months
Contract Completion: October 2005
Value: US $ 5,000,000

Description:

The project comprised of the construction of Three 220KV main substations in various locations throughout Bahrain. The project was part of the Ministry’s infrastructure upgrading project.

The substations are of reinforced concrete construction complete with basement where incoming HV cables terminate with switchgear. The main switchgear is located in an air-conditioned environment and is supported by various control rooms, battery rooms and the like.

The project required careful coordination as several of the substations were built in existing HV electrical facilities. Also as separate contracts were awarded for GIS, transformers and cable installation scheduling the hand over of the works was a critical factor of success. Cebarco guaranteed that the installation contractors were always given access ahead of schedule.







Cebarco Bahrain

P. O. Box 28812
Bldg 1005, Rd 3320
Mahooz 333
Kingdom of Bahrain

Phone: (973) 1772 2237
Fax: (973) 1772 2001
Email: cebarco@kar-group.com

Our Commitment

We strive to deliver a level of service that exceeds the expectations of our customers.

If you have any questions about our products or services, please do not hesitate to contact us. We have friendly, knowledgeable representatives available seven days a week to assist you.

Live View

Get Live view of work-site

 

Cebarco.com.bh